Invoicing will occur in stages outlined below
# Deposit of THIRTY PERCENT (30%) including GST required to schedule in works.
# Stage 1: Rough In - FIFTY PERCENT (50%) including GST
• Includes wiring of proposed site as per specifications on electrical plan and scope of works above. Walkthrough between Wise Elecprotech.
• Wise Elecprotech and customer/builder to be conducted once all wiring has been completed to sign off that it has been checked by both parties and all additional requirements (if any) have been made and/or amendments made.
# Stage 2: Handover - TWENTY PERCENT (20%) including GST.
• All stages of project have been completed. Site has been powered and tested to be in good working order. Walkthrough between Wise Elecprotech and customer/builder to be conducted once testing has been completed to sign off that it has been checked by both parties and all requirements are met as part of the electrical plan agreed upon.
! Please Note
• Temporary switchboard supplied is to be returned at end of construction, a $500.00 plus GST fee will be charged for any damages to board and or removal without our consent.
• Any compliance certificate/s and or as-built documentation will not be issued unless payment in full for the project has been completed. This will be the agreed total amount prior to any work commencing plus any variations.
• All invoices issued have a 7-day payment terms. A reminder will be sent once an invoice becomes overdue, followed by a second a week after that. A third and final reminder will be sent after 1 month of total completion of job before further action is taken. (only for limited customers).
• Any invoices that become overdue may incur late fees.
• Any fees associated with debt collection of overdue invoices will be chargeable back to the customer.
Variations to original quote
• Work outside the specified quote will be quoted and charged separately to the initial quote.
• Any work required to remedy installed cable and or material that has been damaged or stolen by other trades and or people will be quoted and charged separately prior to being repaired and or replaced.
• Damage to any cable, material installed by Wise Elecprotech will be fixed and chargeable to the customer/builder as an additional quotewith proof of interference. Repairs will not proceed until a price to repair has been agreed upon by both parties Wise Elecprotech will notbe liable for any downtime of the project due to this.
Warranty:
# 12 month warranty from the date of practical completion on all works and materials supplied by us in accordance with this warranty.
# In the event of any of the works or materials supplied by us suffering an electrical or mechanical failure or fault within the warranty period we will at our choice either repair the fault, supply the services and materials again or pay for all parts, labour and service call out fees required for the works and materials to be repaired to normal working order subject to the following terms and conditions. The benefits given to you by this warranty are in addition to any other rights and remedies you may have under any law in relation to the goods or services to which this warranty relates. Warranty will not be valid until all invoices issued have been paid in full.
# Warranty is product warranty only, labour will be charged accordingly with call out fee and hourly rate.